Rotary Car Dumper Installation Spring 2017


Our current Rotary Car Dumper installation process began on March 6th.

Here are a few pictures of the progress that has been made so far.

End Rings
Unloading the End Rings from truck. End Rings are shipped in 3 sections that are put together in the field.
End Rings
Both end rings put together.
Standing the second End Ring. This is the entry end ring where the Train Car enters.
pipe truss and end rings
2 standing end rings along with one bottom pipe truss.
Platen and three pipes
The platen has been set and the top pipe truss has been assembled as well.
Spill Wall
Bringing the spill girder in through the end ring to set into place.

RCD

End Ring Sections
The exit end ring is completed and being removed from the table. The entry end rings are in sections and will be moved to the table to be assembled.
Standing End Ring
Standing the first end ring up. This is the exit end ring.
standing rings
Exit and entry end rings are standing.
platen and 2 pipe trusses
The spill side pipe truss has been added and bringing in the platen.
Blocking wall
The crane is preparing to lift the spill girder into place.
spill girder
The spill girder has been set into place.

Dumper

Stay tuned for more progress of our Spring Rotary Car Dumper